22nd May 2020

The end of this week saw level 1 poured, the ground floor drainage approved, the ground floor being backfilled and compacted, and scaffolding start to go up on the North Eastern side of the building!

​

An aerial shot of the structural steel progress, taken from atop our tower crane!

Our brave cadet taking an aerial shot from on top of the crane, sometimes a different perspective lends a better...perspective!

Steel continues to be erected, with columns up to level 5 in place. Comflor will start to go down once the sawtooth edges have been installed.

Ground floor has been backfilled and compacted! The blockwall in the background is also making good progress.

Now the ground floor drainage has been signed off, backfilling up to slab level has started.

Another early start for the Aoraki team, Tuesday saw level 1 being poured!

CONTACT

If you have property, development or construction needs, or know someone who does, we would be delighted to hear from you!

Chris Goldsbury

Director & General Manager

Tel: 027 675 2862

Nigel Butt

Director & Commercial Manager

Tel: 021 227 6262

hiclipart.com.png

Postal Address: PO Box 11012, Manners St 6142

MB_Logo_4Col_RGB-removebg-preview.png
BCITO_Business_qual_seal_black_300dpi_RGB-removebg-preview.png
IWD_sticker_for_web-removebg-preview.png
bottom of page